The first sprint of the 15th quarter of IAM development is complete and we began a large percentage of our commitments as well as provided access to the library for more users the Smithsonian, a highly desirable improvement. The details of Sprint 1 are as follows:

PI-15 Feature Progress

15-1 progress

Committed features 19 change % of total
In Progress 13 - 68%
To Do 5 - 26%
Complete/Deferred 1 - 5%
Additional Objectives Complete 0    

Changes to Commitments this Sprint

  • Completed (1 commitment)
    • SAO library Physical Access - Facilitated Harvard–Smithsonian Center affiliates physical card access to all Harvard Libraries
  • Moved to "In Progress" (13 commitments)
    • Improvements (4): Grouper: load Preferred Name instead of Official Name; Operationalize Phone data updates; Refine the username choices offered during claiming and opt-in; DCE Library access
    • Stability (3): Auth behind Cloud Shield; IIQ Upgrade; SIS Data cleanup
    • Customer (3): Priority HKS Provisioning Improvements; HMS Provisioning Project Plan; Update "MFA Optional" communities to allow Admitted Students to opt-in to Two Step verification
    • Cloud (3): Support customer migrations to Unified LDAP; Move remaining Windows servers out of Oxford Street; Decomm Public LDAP

Operational Statistics

ops stats 15-1

See the attached documents for full details about this PI and IAM project/operational statistics. You can learn more about how we do PI Planning and how to interpret the attached Summary/Priority reports by viewing our "IAM Planning & Progress Reporting" overview post.

pi-15_-_sprint_1_-_summary_report.pdf96 KB
pi-15_-_sprint_1_-_priorities_02.pdf63 KB